Turnkey vs split-package EPC: choosing a contracting model
How full turnkey EPC compares with split-package and balance-of-plant contracting on renewable projects — cost, risk, interfaces and owner capability.
By ANR Horizon Editorial Team · · 4 min read

When an owner contracts for a solar plant or wind farm, one of the first decisions is how to divide the work. Should one contractor deliver everything under a single turnkey contract? Or should the owner split the work into separate packages — equipment supply, civil works, electrical works — and manage the interfaces itself? Each model has real advantages and real risks.
The models
Full turnkey EPC
One contractor is responsible for engineering, procurement and construction of the complete plant, handing it over ready to operate.
Split package
The owner contracts separately for major packages, for example:
- Module or turbine supply
- Inverter or electrical equipment supply
- Civil and structural works
- Electrical installation
- Substation and evacuation
Balance of plant (BoP)
A middle route: the owner buys the main equipment (modules, inverters or turbines) directly, and one contractor does everything else.
Comparing the models
| Turnkey | BoP | Split package | |
|---|---|---|---|
| Single point of responsibility | Yes | Partly | No |
| Interface risk | Contractor | Shared | Owner |
| Price | Higher (includes risk premium) | Moderate | Potentially lowest |
| Owner effort | Lower | Moderate | Highest |
| Equipment choice | Contractor (with owner approval) | Owner | Owner |
| Performance guarantee | Whole plant | Split | Fragmented |
| Lender comfort | Typically highest | Moderate | Depends on owner capability |
Turnkey: pros and cons
Advantages:
- One contract, one counterparty
- Contractor bears interface risk between design, supply and construction
- Whole-plant performance guarantee
- Simpler for lenders
Disadvantages:
- Price includes the contractor's risk premium
- Less owner control over equipment choice
- Owner relies heavily on one contractor's capability
Split package: pros and cons
Advantages:
- Potentially lower total cost
- Owner chooses each supplier and contractor
- Direct relationships with equipment manufacturers
- Flexibility to use specialists for each package
Disadvantages:
- Owner bears interface risk — gaps, overlaps and delays between packages
- Performance guarantees split across contracts, making claims harder
- Higher owner management effort
- Disputes over who caused a problem
Balance of plant: the middle ground
Owners who want control over major equipment — perhaps for procurement requirements, bulk purchasing or manufacturer relationships — but don't want to manage many construction interfaces often choose BoP. The interface between owner-supplied equipment and the BoP contractor (delivery, storage, installation responsibility, damage) must be clearly defined.
Factors in the decision
Owner capability
Does the owner have an experienced team to manage multiple contracts and interfaces? Without it, split packages are risky.
Project size
Larger projects may justify the effort of split packages for cost savings; smaller ones often favour turnkey for simplicity.
Lender requirements
Lenders may require a single point of responsibility or strong interface management.
Equipment procurement
Procurement requirements or owner supply agreements may favour BoP. Check current requirements applicable to equipment sourcing.
Schedule pressure
Turnkey can simplify schedule management; split packages need tight coordination.
Managing interfaces
Whatever the model, interfaces must be explicit:
- Scope matrix listing every item and its responsible party
- Interface agreements or coordination clauses between contractors
- Single integrated schedule
- Clear handover points — when one package hands over to the next
- Owner's engineer coordinating technical interfaces
See how EPC partnerships work.
Common interface problems
- Equipment delivered late, delaying installation contractor
- Foundations not matching structure design
- Cable specifications mismatched between packages
- Damage to owner-supplied equipment — who pays?
- Testing responsibilities unclear
Questions to ask
- Do we have the team to manage multiple contracts?
- What will lenders require?
- How much might split packages save, after accounting for our management cost and risk?
- How will performance guarantees work across packages?
- Who will coordinate interfaces day to day?
Warranties across packages
Under turnkey, one contractor usually stands behind the whole plant during defect liability. Under split packages, each supplier's warranty covers only its own scope, and a fault at the boundary between two packages can leave each pointing at the other. Owners using split packages should plan how warranty claims will be investigated and who will diagnose root causes.
Common mistakes
- Choosing split packages to save cost without management capability
- Underestimating interface risks
- Fragmented performance guarantees with no whole-plant test
- No integrated schedule
- Unclear responsibility for owner-supplied equipment
Hybrid approaches on large programmes
Owners building several projects sometimes mix models: turnkey contracts for early projects while their team builds experience, then BoP or split packages for later ones. Framework agreements with equipment suppliers across a programme can also secure supply while leaving construction contracting flexible. Whatever the mix, carry lessons from each project into the next contract — especially about where interfaces caused trouble.
How we help
Through EPC partner coordination and project management, we help owners compare contracting models, prepare scope matrices and manage interfaces between packages on the owner's side. Construction is performed by independent contractors.
Frequently asked questions
Have a project or land in mind?
Talk to ANR Horizon Group about land, solar, wind or industrial projects — wherever you sit in the process.
More on project development

Project Development
Approvals for renewable projects: an overview
The main permits a solar or wind project may need — land, grid, electrical, environmental, aviation and local — and how to sequence them.
14 October 2026 · 4 min read

Project Development
Building a project documentation file from day one
Why renewable and industrial projects need an organised documentation file from day one, what it should contain, and how it pays off in financing and sale.
14 October 2026 · 4 min read

Project Development
Building a risk register for a renewable project
How to build and use a practical risk register for solar and wind projects — identifying, rating, owning and reviewing risks from land to build.
14 October 2026 · 4 min read