Where renewable project schedules slip — and how to prevent it
The most common causes of delay on solar and wind projects — land, right of way, grid, approvals, equipment, monsoon — and how to reduce each.
By ANR Horizon Editorial Team · · 4 min read

Renewable projects are often planned to tight schedules — driven by tender commitments, financing timelines or buyers' needs. Yet many projects finish later than planned. The causes are rarely mysterious. The same issues appear again and again, and most can be anticipated and reduced with good planning and honest tracking.
1. Land
What goes wrong
- Documentation problems found late — outdated patta, missing heirs, unregistered partitions
- Co-owners who don't agree
- Holdouts on critical parcels
- Boundary disputes discovered during survey
Prevention
- Map ownership and check records before committing to layouts
- Start resolving record issues early. See preliminary checks vs legal due diligence.
- Secure critical parcels first
- Keep a parcel register with issues and owners
2. Right of way
What goes wrong
- Access roads, cable routes and lines cross land not originally considered
- One landowner along a route refuses
- Route changes after engineering
Prevention
- Plan routes alongside layouts
- Identify alternatives for critical segments
- Secure route agreements before construction depends on them
See wind project right of way.
3. Grid connectivity
What goes wrong
- Substation bay or capacity not ready
- Evacuation line delayed by approvals or right of way
- Upstream transmission not complete
Prevention
- Screen grid availability before land work
- Track utility schedules closely
- Treat the evacuation line as a separate project with its own schedule
4. Approvals
What goes wrong
- Applications waiting on each other
- Incomplete submissions
- Requirements changed since planning
- Conditions not met in time
Prevention
- Map approvals and their dependencies
- Maintain an approvals tracker. See renewable project approvals overview.
- Check current requirements early
5. Equipment supply
What goes wrong
- Long lead times for transformers, switchgear and turbines
- Manufacturing delays
- Shipping and customs delays
- Equipment failing factory or site inspection
Prevention
- Order long-lead items early
- Track supplier progress, not just delivery dates
- Inspect at factory before shipping
6. Weather
What goes wrong
- Monsoon rains make sites inaccessible, flood trenches and halt earthworks
- High winds stop crane work on wind sites
- Extreme heat affects workforce productivity
Prevention
- Plan earthworks and foundations outside heavy-rain periods where possible
- Include realistic weather allowances
- Prepare temporary drainage. See solar site drainage and flood risk.
7. Community
What goes wrong
- Work stopped by landowners or villagers over unpaid compensation, crop damage or access
- Disputes over local employment
- Damage to village roads by construction traffic
Prevention
- Engage before mobilising
- Pay compensation promptly
- Maintain a grievance process
- Repair damage quickly
See landowner relations during construction.
8. Interfaces
What goes wrong
- Scope gaps between owner and EPC, or between packages
- Late design approvals
- Owner-supplied equipment arriving late
- Responsibilities unclear for utility works
Prevention
- Scope matrix and interface register. See turnkey vs split-package EPC.
- Agreed turnaround times for design reviews
- Single integrated schedule
9. Mobilising too early
What goes wrong
Mobilising before the site is ready creates idle time, claims and frustration.
Prevention
Run a readiness review. See project readiness checklist.
10. Commissioning
What goes wrong
- Punch list items accumulate
- Tests fail and must be repeated
- Utility inspections and approvals for energisation delayed
Prevention
- Plan commissioning early
- Clear punch list items progressively
- Book inspections well in advance
See commissioning and handover checklist.
Early warning
Delays rarely appear suddenly. They build through small slips that are reported optimistically. Good practice:
- Track leading indicators — parcels signed, approvals submitted, designs approved — not just construction progress
- Use a risk register that is reviewed honestly. See risk register for renewable projects.
- Encourage reporting of problems early, without blame
Recovering a slipping schedule
When delays occur, recovery options include resequencing work to areas that are ready, adding resources on critical activities, fast-tracking decisions and approvals, and, where possible, overlapping activities that were planned in sequence. Each has cost and risk. The earlier a delay is recognised, the more recovery options remain available — which is the strongest argument for honest reporting.
Common mistakes
- Optimistic schedules that ignore known risks
- Focusing only on construction progress
- Treating land and grid as someone else's problem
- No integrated schedule across all parties
- Hiding bad news until it can't be hidden
How we help
Through project management and execution support, we work on the owner's side to track the issues that cause most delays — land, right of way, approvals, community and interfaces — and help resolve them before they reach the critical path.
Frequently asked questions
Have a project or land in mind?
Talk to ANR Horizon Group about land, solar, wind or industrial projects — wherever you sit in the process.
More on project development

Project Development
Approvals for renewable projects: an overview
The main permits a solar or wind project may need — land, grid, electrical, environmental, aviation and local — and how to sequence them.
14 October 2026 · 4 min read

Project Development
Building a project documentation file from day one
Why renewable and industrial projects need an organised documentation file from day one, what it should contain, and how it pays off in financing and sale.
14 October 2026 · 4 min read

Project Development
Building a risk register for a renewable project
How to build and use a practical risk register for solar and wind projects — identifying, rating, owning and reviewing risks from land to build.
14 October 2026 · 4 min read