Tamil Nadu releases Battery Energy Storage Systems Policy 2026

Tamil Nadu's new BESS policy targets at least 2.5 GW / 10 GWh of storage, waives transmission charges and asks new solar projects to add storage.

Reported:
Summary published:

What happened

The Tamil Nadu government released its Battery Energy Storage Systems Policy, 2026 on 3 November 2026, according to a PTI report carried by Oneindia. As reported, the policy:

  • Targets at least 2.5 GW (10 GWh) of storage during its operative period
  • Names TNGECL as the nodal agency
  • Covers standalone storage and storage co-located with renewable plants
  • Offers a full waiver of transmission and wheeling charges for 10 years for eligible projects commissioned within the policy window, where discharged energy is used in the state
  • Requires new solar and hybrid projects above 1 MW commissioned from April 2027 to add storage of at least 10% of capacity with four-hour duration
  • Sets safety, environmental and cybersecurity expectations

Why it matters

The storage requirement changes the cost, land and design of new solar projects in the state, and the charge waiver improves the case for standalone storage. We explain the details in Tamil Nadu's BESS Policy 2026 explained and adding storage to new solar projects. Check the notified policy text for exact provisions.